Environmental assessments waived for major infrastructure projects

Large-scale projects for the roll-out of gas, electricity, solar and other infrastructure projects will be exempted from the need for environmental authorization in terms of notices gazetted by the government at the end of July.

After nearly five months of lockdown, and an estimated 3 million jobs lost, the government is under pressure to fast-track massive infrastructure developments to kick-start an already sputtering economy, said Rob Hutchinson, MD of Dear South Africa, a non-profit organisation, suggesting that the move is one of the possible motivations for the proposed exemptions.

The National Environmental Management Act allows the minister to exclude certain activities and projects from the need to obtain environmental authorisation provided an “environmental management instrument” is developed that avoids, manages and mitigates environmental risks associated with the projects.

This is seen as a way of speeding up infrastructure development without having to go through the often agonising process of undertaking environmental assessments and approvals. 

Going through the usual environmental hoops can take several years, said Hutchinson, and that adds to the eventual cost of infrastructural development.

Environmental concerns not neglected

The “environmental management instrument” is supposed to take care of that, though there is understandable suspicion that this may be a way of side-stepping environmental regulations imposed on all other projects that do not enjoy exemptions.

A series of environmental authorisation exemptions have been proposed that would cover virtually all major gas pipeline projects currently under consideration. This is achieved through the adoption of a generic environmental management programme for gas pipeline infrastructure.

Exemptions are also proposed for electricity transmission and distribution powerline infrastructure falling within certain geographical areas known as Strategic Transmission Corridors.

Five primary power corridors

There are five primary corridors (and two extensions) for electricity transmission and distribution: from Limpopo to Gauteng; Gauteng to the Northern Cape; Gauteng to the Western Cape; Kwazulu-Natal to the Western Cape; and the Western Cape to the Northern Cape. 

Should more than 10% of the proposed electricity transmission and distribution powerline infrastructure fall outside these corridors, the entire project is subject to the Environmental Impact Assessment Regulations which were published in 2014.

Image via Adobe Stock

A new environmental standard has been developed for these geographical areas which would exclude electricity transmission and distribution powerline infrastructure from having to obtain environmental authorisation.

The Minister of Forestry, Fisheries and the Environment has also set management and mitigation standards that would exempt landcare, ecosystems and working for water projects from the need to obtain environmental authorisation.

The public is also being asked to provide input on procedures to be followed when applying for, and deciding on Renewable Energy Development Zones (REDZ).

The opportunity for the public to comment closes on 4 September 2020.